Saltar al contenido
Volver a la búsqueda
H2B

Rebar Workers

Genuine Builders, Inc.

Compensación

$47.86/hora

Salario mensual estimado:
$8,295.73
Estimado total del contrato completo:
$6,016.69
Salario de tiempo extra:
$71.79/hora
Deducciones de salario:
All deductions from the worker’s paycheck will be made as required by law. Any advances will be deducted with the consent of the employee. The employer will provide housing as an option to employees living outside the regular commuting distance. Employees who elect to live in the housing will have an additional $250.00 deducted per biweekly paycheck for rent and utilities.

Los estimados se calculan a partir de la tarifa de salario, las horas semanales y las fechas de contrato del registro oficial. No son una garantía de ingreso real.

Detalle del trabajo

Fechas:
9 de diciembre de 2026 – 31 de diciembre de 2026
puestos:
6
Horas semanales:
40
Vivienda:
Se proporciona
Transporte:
Se proporciona

Descripción del trabajo

Your attention is requested to the following letter in support of Genuine Builders, Inc.s (GBI) request for six (6) temporary Rebar Workers to supply our seasonal temporary need in Rochester, Indiana. GBI of Arlington, South Dakota is a concrete sub-contractor that has provided specialized concrete construction services for the last twenty-eight (28) years. The Rebar Workers will: Position and secure steel bars or mesh in concrete forms in order to reinforce concrete. Able to operate wire reel, klein pliers and hand tools to fasten and bend rebar. The Rebar Workers must have six (6) months of tying rebar for concrete construction experience and be able to handle temperature extremes and lift and carry 75 lbs. for 75 yards. They will work some weekends and travel to worksites within area of intended employment. For more information regarding the company and photographs of some of its projects, see Exhibit A. Schedule of Operations Each year, GBIs schedule of operations is as follows: GBIs annual schedule of operations begins in April and ends in December. GBI will begin working on projects in Rochester, Indiana in November and seeks to have H-2B workers on site as soon as possible. Work will continue through December 31st. In January, the weather is too cold to perform concrete work. Therefore, the company does not perform concrete work from January through March. Work that is performed at the end of a project includes cleaning up, which can take up to a month depending on the size of the project. Clean up includes the following duties to get rid of waste materials and prepare the site for the client: o Grind metal inserts in the concrete so that the top is level and completely flat. o Caulk around concrete. o Patch air pockets in concrete. o Clean up excess concrete which has seeped out from around the forms. o General clean-up including, disposal of excess concrete dumped by pump trucks at the site. o Dispose of used or damaged lumber, pick up debris and load excess supplies. o Clean and oil forms, then load them onto the trailer. o Forms must be stacked so they are not overweight on the trailer. Temporary Seasonal Need GBI has a seasonal need that is traditionally tied to a season of the year by an event which is of a recurring nature, specifically the weather that permits concrete construction. In the late spring and early summer, the company experiences an increased demand for its work as the weather warms to allow cement construction. During the winter months, from January through March, the weather is too cold for proper setting of concrete. Excavation of concrete footings is more difficult, if not impossible. Cold Weather Concreting Reported by ACI Committee 306, Section 1.1, Definition of cold weather, defines cold weather as a period when, for more than 3 consecutive days, the following conditions exist: 1) The average daily air temperature is less than 40F; and 2) The air temperature is not greater than 50F for more than one-half of any 6-hr period. The average daily air temperature is the average of the highest and lowest temperatures occurring during the period from midnight to midnight. Cold weather, as defined in this report, usually starts during fall and usually continues until spring. Exhibit B. The cold season in Rochester, Indiana lasts for over three (3) months, with an average daily high temperature of 32 F in January and 31 inches of average annual snowfall. See Exhibit C, Average Weather in Rochester, Indiana, United States. Therefore, concrete work does not start until the weather warms up in April, and there is always a rush to pour as much cement as possible in the warm-weather months that permit proper placing and curing. This naturally creates a seasonal need for concrete construction in the State of Indiana during the dates of need, and not year-round. Please see attached.

Ubicación

7901 South 100 West, Rochester, IN 46975

Este registro confirma que la oportunidad aparece en la fuente oficial de datos del Departamento de Trabajo citada, en el momento indicado. No prueba disponibilidad actual, no garantiza selección, ni autoriza a un reclutador a cobrarte dinero. No pagues cuotas de reclutamiento no autorizadas.

Ver la fuente oficial del Departamento de Trabajo de EE. UU.

Última actualización: 7 de octubre de 2026